Home / Critical Path Analysis

3.8 · Paper 2B

Critical Path Analysis

Activity networks, early and late times, critical paths and float — how to plan a project and find the activities that cannot slip.

Jump to a sub-skill

Practise one skill at a time

Each sub-skill has its own animated explanation, step-by-step notes, a past-paper style question and a short worksheet with mark scheme.

See it in action

Animated explanation

Scroll to the graphic and it plays by itself — press Replay to watch it again.

Activity networks

3.8a▾

A project is split into activities, each with a duration and a list of immediate predecessors (activities that must finish first). A precedence table records this, and an activity network draws it: a box for each activity with arrows from each immediate predecessor. Following an algorithm — a clear step-by-step procedure — is the same skill used to build these networks.

Early and late times

3.8b▾

The forward pass finds each activity's early time (earliest start): take the largest of (early time + duration) over its predecessors. The backward pass finds each late time (latest finish): take the smallest of (late time of a successor − its duration). The minimum completion time is the longest route through the network.

Critical activities, float and Gantt charts

3.8c▾

Float = late time − early time − duration. Activities with zero float are critical; they form the critical path — a delay to any of them delays the whole project. A Gantt chart shows each activity as a bar with its float dashed. Shortening (crashing) only helps if you shorten a critical activity, and a new critical path may then appear.

Worked example

A project has activities A (3 days), B (5 days), C (4 days, after A), D (3 days, after B) and E (3 days, after C and D). Find the minimum completion time and the critical path.

Forward pass: A and B start at 0. C starts at 3. D starts at 5. E must wait for both C (3+4 = 7) and D (5+3 = 8), so E starts at max(7, 8) = 8. Minimum completion time = 8 + 3 = 11 days.

Backward pass: E's late time is 11, so C and D must finish by 11 − 3 = 8. B must finish by 8 − 3 = 5; A by 8 − 4 = 4.

Float: A = 4−0−3 = 1; B = 5−0−5 = 0; C = 8−3−4 = 1; D = 8−5−3 = 0; E = 11−8−3 = 0. Critical path: B → D → E.

Exam tip. Write early times in the left cell and late times in the right cell of every box as you go. Most lost marks come from taking the smaller value on the forward pass or the larger value on the backward pass — remember: forward = largest, backward = smallest.